Clifton Corridor iconRate the Clifton Corridor Screen 2 Alternatives 

Please review the information below and rate each technology in terms of how appropriate it is for the Clifton Corridor.  The technologies under consideration include, light rail (LRT1), bus rapid transit (BRT1), and heavy rail transit (HRT4).  Please be aware that all transit options are proposed to operate in tunnels below Lenox Road, the intersection of North Decatur and Clairmont Roads, and portions of Scott  Boulevard.  HRT4 terminates beneath the intersection of North  Decatur and Clairmont Roads.


BRT 1 provides 8.3 miles of bus rapid service from Lindbergh Center to Avondale Station that operates adjacent to the CSX rail right-of-way through the CDC/Emory University area to Clairmont Road at North Decatur Road. BRT1 would then extend south and run along the medians of Scott Boulevard, North Decatur Road, DeKalb Industrial Way and terminate at Avondale Station.

  

BRT diagram updated

Projects Ridership:

  • Daily Boardings: 15,300
  • New Riders: 4,000

Estimated Costs:

  • Capital: $873M ($105M per mile)
  • Right of Way: $10.1M
  • Annual O&M: $14M

Projected Travel Times to Emory/CDC:

  • From Lindbergh Center: 13 min
  • From Atlanta Airport: 43 min
  • From North Springs: 38 min

Projected Employment within ½ mile of Stations: 15 jobs/acres

Level of Community Support: Moderate

Please rate BRT 1 on a scale of 1 to 5, with 1 being “least appropriate for transit in the Clifton Corridor,” and 5 being “most appropriate.

 


LRT 1 provides 8.3 miles of light rail service from Lindbergh Center to Avondale Station that operates adjacent to the CSX rail right-of-way through the CDC/Emory University area to Clairmont Road at North Decatur Road. LRT1 would then extend south and run along the medians of Scott Boulevard, North Decatur Road, DeKalb Industrial Way and terminate at Avondale Station.

Clifton diagram 2

Projects Ridership:

Daily Boardings: 17,500

New Riders: 5,300

Estimated Costs:

  • Capital: $988M ($118.7M per mile)
  • Right of Way: $10.1M
  • Annual O&M: $15.3M

Projected Travel Times to Emory/CDC:

  • From Lindbergh Center: 13 min
  • From Atlanta Airport: 43 min
  • From North Springs: 38 min

Projected Employment within ½ mile of Stations: 15 jobs/acres

Level of Community Support: High

Please rate LRT 1 on a scale of 1 to 5, with 1 being “least appropriate for transit in the Clifton Corridor,” and 5 being “most appropriate.”


HRT 4 provides heavy rail service that operates adjacent to CSX rail right-of-way from Lindbergh Center through the CDC/Emory University area, and then terminates at Clairmont Road at North Decatur Road. Local bus transfer is available for connection to Avondale Station. As HRT4 is compatible with the existing MARTA rail system, it is able to provide direct rail service from the Airport, Doraville, and North Springs without transferring at Lindbergh Center.

Clifton diagram 3

Projects Ridership:

Daily Boardings: 18,400

New Riders: 6,900

Estimated Costs:

  • Capital: $1.36B ($282.7M per mile)
  • Right of Way: $3.2M
  • Annual O&M: $28M

Projected Travel Times to Emory/CDC:

  • From Lindbergh Center: 12 min
  • From Atlanta Airport: 41 min
  • From North Springs: 33 min

Projected Employment within ½ mile of Stations: 17.6 jobs/acres

Level of Community Support: Moderate

Please rate HRT 4 on a scale of 1 to 5, with 1 being “least appropriate for transit in the Clifton Corridor,” and 5 being “most appropriate.”

Please provide your comments below:
 

 Name:    

Address :   

The Clifton Corridor Alternatives Analysis welcomes your input!  Please submit your ideas and comments to:

Leah Vaughan, Sycamore Consulting
195 Arizona Avenue, Unit LW 4
Atlanta, Georgia 30309
404-377-9147
FAX (404) 377-9091   LeahVaughan@SycamoreConsulting.net

Deadline: November 8, 2011

   Metropolitan Atlanta Rapid Transit Authority 
image


Plan Your Trip      |     How to Ride MARTA   |      Advertise with MARTA    |     Contact Us    |    Sitemap    |    Privacy Policy & Disclaimers

Select a Language:

Regional System Partners:

Spanish French Japanese Chinese Korean German

Copyright ©2009 MARTA. All Rights Reserved.

CCT GRTA Xpress Gwinnett Transit
 
  layout image layout image layout image